81. Preparation of Engineering Projects of Deriner Dam Relocation Roads, Bridges 1,2, and 3 at Artvin-Erzurum State Highway at Deriner Dam and Hydroelectrical Power Plant Project
Project Details
-Preparation of Köprü-1 Bridge (L=48 m, Simple Span, Steel-Concrete Composite superstructure)
-Preparation of Köprü-2 Bridge (L=55 m, Simple Span, Steel-Concrete Composite superstructure)
-Preparation of Köprü-3 Bridge (L=48 m, Simple Span, Steel-Concrete Composite superstructure)
-Preparation of Type G-E-K Retaining Walls Projects ( h = 4 m – 20 m )
-Preparation of RT-1 Tunnel Cut&Cover Portal Structure Projects
(Arc and Box Section)
-Preparation of RT-2 Tunnel Cut&Cover Portal Structure Projects
(Arc and Box Section)
-Preparation of T-1 Tunnel Cut&Cover Portal Structure Projects
(Arc and Box Section)
-Preparation of RT-2 Tunnel Cut&Cover Portal Structure Projects
(Arc and Box Section)
Employer
General Directorate of Highways 10’th Division Directorate